As prescribed in 15.209(b),
(1) Except as provided in paragraph (b)(2) of this section, the contracting officer shall insert the clause at 52.215-2, Audit and Records-Negotiation (10 U.S.C. 2313, 41 U.S.C. 4706, and Audit Requirements in the OMB Uniform Guidance at 2 CFR part 200, subpart F), in solicitations and contracts except those for-
(i) Acquisitions not exceeding the simplified acquisition threshold;
(ii) The acquisition of utility services at rates not exceeding those established to apply uniformly to the general public, plus any applicable reasonable connection charge; or
(iii) The acquisition of commercial items exempted under 15.403-1.
(2) (i) When using funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009 (Pub. L. 111-5)-
(A) The exceptions in paragraphs (b)(1)(i) through (b)(1)(iii) are not applicable; and
(B) Use the clause with its Alternate I.
(ii) (A) In the case of a bilateral contract modification that will use funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009, the contracting officer shall specify applicability of Alternate I to that modification.
(B) In the case of a task- or delivery-order contract in which not all orders will use funds appropriated or otherwise made available by the American Recovery and Reinvestment Act of 2009, the contracting officer shall specify the task or delivery orders to which Alternate I applies.
(3) For cost-reimbursement contracts with State and local Governments, educational institutions, and other nonprofit organizations, the contracting officer shall use the clause with its Alternate II.
(4) When the head of the agency has waived the examination of records by the Comptroller General in accordance with 25.1001, use the clause with its Alternate III.
Audit and Records-Negotiation (Jun 2020) Alternate I (Mar2009)
(a) As used in this clause, “records” includes books, documents, accounting procedures and practices, and other data, regardless of type and regardless of whether such items are in written form, in the form of computer data, or in any other form.
(b) Examination of costs. If this is a cost-reimbursement, incentive, time-and-materials, labor-hour, or price redeterminable contract, or any combination of these, the Contractor shall maintain and the Contracting Officer, or an authorized representative of the Contracting Officer, shall have the right to examine and audit all records and other evidence sufficient to reflect properly all costs claimed to have been incurred or anticipated to be incurred directly or indirectly in performance of this contract. This right of examination shall include inspection at all reasonable times of the Contractor’s plants, or parts of them, engaged in performing the contract.
(c) Certified cost or pricing data. If the Contractor has been required to submit certified cost or pricing data in connection with any pricing action relating to this contract, the Contracting Officer, or an authorized representative of the Contracting Officer, in order to evaluate the accuracy, completeness, and currency of the certified cost or pricing data, shall have the right to examine and audit all of the Contractor’s records, including computations and projections, related to-
(1) The proposal for the contract, subcontract, or modification;
(2) The discussions conducted on the proposal(s), including those related to negotiating;
(3) Pricing of the contract, subcontract, or modification; or
(4) Performance of the contract, subcontract or modification.
(d) Comptroller General or Inspector General.
(1) The Comptroller General of the United States, an appropriate Inspector General appointed under section 3 or 8G of the Inspector General Act of 1978 ( 5 U.S.C. App. ), or an authorized representative of either of the foregoing officials, shall have access to and the right to-
(i) Examine any of the Contractor’s or any subcontractor’s records that pertain to and involve transactions relating to this contract or a subcontract hereunder; and
(ii) Interview any officer or employee regarding such transactions.
(2) This paragraph may not be construed to require the Contractor or subcontractor to create or maintain any record that the Contractor or subcontractor does not maintain in the ordinary course of business or pursuant to a provision of law.
(e) Reports. If the Contractor is required to furnish cost, funding, or performance reports, the Contracting Officer or an authorized representative of the Contracting Officer shall have the right to examine and audit the supporting records and materials, for the purpose of evaluating-
(1) The effectiveness of the Contractor’s policies and procedures to produce data compatible with the objectives of these reports; and
(2) The data reported.
(f) Availability. The Contractor shall make available at its office at all reasonable times the records, materials, and other evidence described in paragraphs (a), (b), (c), (d), and (e) of this clause, for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in subpart 4.7, Contractor Records Retention, of the Federal Acquisition Regulation (FAR), or for any longer period required by statute or by other clauses of this contract. In addition-
(1) If this contract is completely or partially terminated, the Contractor shall make available the records relating to the work terminated until 3 years after any resulting final termination settlement; and
(2) The Contractor shall make available records relating to appeals under the Disputes clause or to litigation or the settlement of claims arising under or relating to this contract until such appeals, litigation, or claims are finally resolved.
(g) (1) Except as provided in paragraph (g)(2) of this clause, the Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts under this contract. The clause may be altered only as necessary to identify properly the contracting parties and the Contracting Officer under the Government prime contract.
(2) The authority of the Inspector General under paragraph (d)(1)(ii) of this clause does not flow down to subcontracts.
The clause may be altered only as necessary to identify properly the contracting parties and the Contracting Officer under the Government prime contract.
(End of clause)
(g) (1) Except as provided in paragraph (g)(2) of this clause, the Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts under this contract. The clause may be altered only as necessary to identify properly the contracting parties and the Contracting Officer under the Government prime contract. (2) The authority of the Inspector General under paragraph (d)(1)(ii) of this clause does not flow down to subcontracts.