As prescribed in 1836.570(c), the contracting officer shall insert the clause at 1852.236-73, Hurricane Plan, in solicitations and contracts for construction at sites that experience hurricanes.
HURRICANE PLAN (DEC 1988)
In the event of a hurricane warning, the Contractor shall–
(a) Inspect the area and place all materials possible in a protected location;
(b) Tie down, or identify and store, all outside equipment and materials;
(c) Clear all surrounding areas and roofs of buildings, or tie down loose material, equipment, debris, and any other objects that could otherwise be blown away or blown against existing buildings; and
(d) Ensure that temporary erosion controls are adequate.
(End of clause)