FAR 52.234-3 Notice of Earned Value Management System-Postaward Integrated Baseline Review. Basic (Nov 2016) (Current)

As prescribed in 34.203(b), the contracting officer shall insert a provision that is substantially the same as the provision at 52.234-3, Notice of Earned Value Management System-Postaward Integrated Baseline Review, in solicitations for contracts that require the contractor to use an Earned Value Management System (EVMS) and for which the Government requires an Integrated Baseline Review (IBR) after contract award.

DoD: 234.203(1) For cost or incentive contracts valued at $20,000,000 or more, and for other contracts for which EVMS will be applied in accordance with 234.201(1)(iii) and (iv), use the provision at 252.234-7001, Notice of Earned Value Management System, instead of the provisions at FAR 52.234-2, Notice of Earned Value Management System – Pre-Award IBR, and FAR 52.234-3, Notice of Earned Value Management System – Post-Award IBR, in the solicitation.

Notice of Earned Value Management System-Postaward Integrated Baseline Review (Nov 2016)

(a) The offeror shall provide documentation that the Cognizant Federal Agency has determined that the proposed earned value management system (EVMS) complies with the EVMS guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at time of solicitation).

(b) If the offeror proposes to use a system that has not been determined to be in compliance with the requirements of paragraph (a) of this provision, the offeror shall submit a comprehensive plan for compliance with the EVMS guidelines.

    (1) The plan shall—

        (i) Describe the EVMS the offeror intends to use in performance of the contracts;

        (ii) Distinguish between the offeror’s existing management system and modifications proposed to meet the guidelines;

        (iii) Describe the management system and its application in terms of the EVMS guidelines;

        (iv) Describe the proposed procedure for administration of the guidelines, as applied to subcontractors; and

        (v) Provide documentation describing the process and results of any third-party or self-evaluation of the system’s compliance with the EVMS guidelines.

    (2) The offeror shall provide information and assistance as required by the Contracting Officer to support review of the plan.

    (3) The Government will review and approve the offeror’s plan for an EVMS before contract award.

    (4) The offeror’s EVMS plan must provide milestones that indicate when the offeror anticipates that the EVM system will be compliant with the EIA-748 guidelines.

(c) Offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected, planned for application of the guidelines. The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS guidelines.

(End of provision)

NONE, but (c), the offerors shall identify the major subcontractors, or major subcontracted effort if major subcontractors have not been selected, planned for application of the guidelines. The prime Contractor and the Government shall agree to subcontractors selected for application of the EVMS guidelines.

Prime’s Interest;
Contracts ✖ 
⚠ <252.234-7001 Basic

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!