This clause has not been authorized for official release. We recommend deferring to the text of the clause in your RFP or contract.
(a) The effort to be performed under this contract includes a series of systems engineering technical reviews to review the design/development of the system and assess the progress towards meeting the technical and/or performance requirements set forth in this contract. The reviews will provide an independent assessment of the emerging design/development of the system against the contractual requirements and user’s capabilities requirements.
(b) Government express or implied approval of any particular technical approach or deliverable does not alter the Contractor's responsibility to meet the requirements of the contract. The contractor maintains design responsibility for the system at all times.
(End of clause)
NONE