As prescribed in 48 CFR 1309.507-1,
(a), insert provision 1352.209-70, Potential Organizational Conflict of Interest, substantially as written, in solicitations when the contracting officer determines there is a potential organizational conflict of interest.
(b) Insert the clause with its Alternate I when the contracting officer determines the basic clause should not be modified.
Potential Organizational Conflict of Interest (APR 2010)
(a) There is a potential organizational conflict of interest (see FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest) due to [state the nature of the potential conflict]. Accordingly:
(1) Restrictions are needed to ensure that (state the nature of the proposed restraint and the applicable time period).
(2) As a part of the proposal, the offeror shall provide the Contracting Officer with complete information regarding previous or ongoing work that is in any way associated with the contemplated acquisition.
(b) If award is made to the offeror, the resulting contract may include an organizational conflict of interest limitation applicable to subsequent Government work, at either a prime contract level, at any subcontract tier, or both. During evaluation of proposals, the Government may, after discussions with the offeror and consideration of ways to avoid the conflict of interest, insert a provision in the resulting contract that shall disqualify the offeror from further consideration for award of specified future contracts.
(c) The organizational conflict of interest clause included in this solicitation may be modified or deleted during negotiations.
(End of clause)
NONE