As prescribed in 48 CFR 1301.602-3,
(a) Insert clause 1352.201-71, Ratification Release, in a contract document under which payment is made for unauthorized commitments after a ratification has been processed.
(b) (1) Unauthorized commitments occur when the Department accepts goods or services in the absence of an enforceable contract entered into by an authorized official. It is the policy of DOC that all acquisitions are to be made only by Government officials having authority to make such acquisitions. Acquisitions made by other than authorized personnel are contrary to Departmental policy and the Department is not bound by any formal or informal type of agreement or contractual commitment which is made by persons who are not delegated contracting authority. Payment for goods or services accepted in the absence of an authorized commitment may be made only through the ratification process. Unauthorized commitments may be considered matters of serious misconduct and may subject the responsible employees to appropriate disciplinary actions.
(2) The delegation of the ratification authority is set forth in CAM 1301.70. All requests for ratification must fully explain the circumstances that gave rise to the unauthorized commitment and detail, if appropriate, any disciplinary action taken with respect to any responsible employee. Ratifications may be approved only if all criteria in FAR 1.602-3 have been met.
Ratification Release (APR 2010)
(a) The Government agrees to pay the contractor $____ for the following items/services:
(b) In consideration for the sum stated above, which is to be paid to the Contractor, or its assignees, the Contractor, upon payment of the said sum by the UNITED STATES OF AMERICA (hereinafter called the Government), does remise, release, and discharge the Government, its officers, agents, and employees of and from all liabilities, obligations, claims, and demands whatsoever under or arising from the said contract, except:
(1) Specified claims in stated amounts or in estimated amounts where the amounts are not susceptible of exact statement by the Contractor, as follows: (or state “None”).
(2) Claims, together with reasonable expenses incidental thereto, based upon the liabilities of the Contractor to third parties arising out of the performance of this contract, which are not known to the Contractor on the date of the execution of this release and of which the Contractor gives notice in writing to the Contracting Officer within the period specified in said contract.
(3) Claims for reimbursement of costs (other than expenses of the Contractor by reason of his indemnification of the Government against patent liability) including reasonable expenses incidental thereto, incurred by the Contractor under any provisions of the said contract relating to patents.
(c) The Contractor agrees, in connection with patent matters and with claims which are not released as set forth above, that it will comply with provisions of the said contract, including without limitation, those provisions relating to notification to the Contracting Officer and relating to the defense or prosecution of litigation.
Contractor's Signature:
Date:
(End of clause)