FAR 52.234-4 Earned Value Management System. Basic (Nov 2016) (Current)

As prescribed in 34.203(c), the contracting officer shall insert a clause that is substantially the same as the clause at FAR 52.234-4, Earned Value Management System, in solicitations and contracts that require a contractor to use an EVMS.

DoD: 234.203(2). For cost or incentive contracts valued at $20,000,000 or more, and for other contracts for which EVMS will be applied in accordance with 234.201(1)(iii) and (iv), use the clause at 252.234-7002, Earned Value Management System, instead of the clause at FAR 52.234-4, Earned Value Management System, in the solicitation and contract.

Earned Value Management System (Nov 2016)

(a) The Contractor shall use an earned value management system (EVMS) that has been determined by the Cognizant Federal Agency (CFA) to be compliant with the guidelines in Electronic Industries Alliance Standard 748 (EIA-748) (current version at the time of award) to manage this contract. If the Contractor’s current EVMS has not been determined compliant at the time of award, see paragraph (b) of this clause. The Contractor shall submit reports in accordance with the requirements of this contract.

(b) If, at the time of award, the Contractor’s EVM System has not been determined by the CFA as complying with EVMS guidelines or the Contractor does not have an existing cost/schedule control system that is compliant with the guidelines in EIA-748 (current version at time of award), the Contractor shall—

    (1) Apply the current system to the contract; and

    (2) Take necessary actions to meet the milestones in the Contractor’s EVMS plan approved by the Contracting Officer.

(c) The Government will conduct an Integrated Baseline Review (IBR). If a pre-award IBR has not been conducted, a post award IBR shall be conducted as early as practicable after contract award.

(d) The Contracting Officer may require an IBR at—

    (1) Exercise of significant options; or

    (2) Incorporation of major modifications.

(e) Unless a waiver is granted by the CFA, Contractor proposed EVMS changes require approval of the CFA prior to implementation. The CFA will advise the Contractor of the acceptability of such changes within 30 calendar days after receipt of the notice of proposed changes from the Contractor. If the advance approval requirements are waived by the CFA, the Contractor shall disclose EVMS changes to the CFA at least 14 calendar days prior to the effective date of implementation.

(f) The Contractor shall provide access to all pertinent records and data requested by the Contracting Officer or a an authorized representative as necessary to permit Government surveillance to ensure that the EVMS conforms, and continues to conform, with the performance criteria referenced in paragraph (a) of this clause.

(g) The Contractor shall require the subcontractors specified below to comply with the requirements of this clause: [Insert list of applicable subcontractors.]

________________________________________________ 
________________________________________________ 
________________________________________________ 
________________________________________________

(End of clause)

NONE, but (g), the Contractor shall require the subcontractors specified below to comply with the requirements of this clause: [Insert list of applicable subcontractors.]

Mandatory (Exception);
Applies to solicitations and contracts that require a contractor to use an EVMS. Flow down of EVMS requirements is required only for those subcontractors expressly identified in the Paragraph (g). DoD: 234.203(2). For cost or incentive contracts valued at $20,000,000 or more, and for other contracts for which EVMS will be applied in accordance with 234.201(1)(iii) and (iv), use the clause at 252.234-7002, Earned Value Management System, instead of the clause at FAR 52.234-4, Earned Value Management System, in the solicitation and contract.
⚠ <252.234-7002 Basic

52.203-16 Preventing Personal Conflicts of Interest.

52.212-3 Offeror Representations and Certifications—Commercial Items.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

52.222-36 Equal Opportunity for Workers with Disabilities.

52.228-15 Performance and Payment Bonds—Construction.

52.212-3 Offeror Representations and Certifications—Commercial Items.

52.212-3 Offeror Representations and Certifications—Commercial Items.

52.219-6 Notice of Total Small Business Set-Aside.

52.219-7 Notice of Partial Small Business Set-Aside.

52.212-3 Offeror Representations and Certifications-Commercial Items.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

52.212-3 Offeror Representations and Certifications-Commercial Items.

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns.

52.219-6 Notice of Total Small Business Set-Aside.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

52.219-18 Notification of Competition Limited to Eligible 8(a) Concerns

52.225-7 Waiver of Buy American Statute for Civil Aircraft and Related Articles.

52.228-15 Performance and Payment Bonds-Construction.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.212-3 Offeror Representations and Certifications-Commercial Items.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

252.242-7005 Contractor Business Systems.

252.209-7011 Representation for Restriction on the Use of Certain Institutions of Higher Education.

252.225-7037 Evaluation of Offers for Air Circuit Breakers.

252.225-7019 Restriction on Acquisition of Anchor and Mooring Chain.

252.225-7062 Restriction on Acquisition of Large Medium-Speed Diesel Engines.

252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.

252.247-7023 Transportation of Supplies by Sea.

252.225-7037 Evaluation of Offers for Air Circuit Breakers.

752.231-71 Salary supplements for HG employees.

952.250-70 Nuclear hazards indemnity agreement.

952.227-84 Notice of right to request patent waiver.

52.203-16 Preventing Personal Conflicts of Interest.

52.209-3 First Article Approval-Contractor Testing.

52.209-4 First Article Approval-Government Testing.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.215-17 Waiver of Facilities Capital Cost of Money.

52.219-18 Notification of Competition Limited to Eligible 8(a) Participants.

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns.

52.219-6 Notice of Total Small Business Set-Aside.

52.219-7 Notice of Partial Small Business Set-Aside.

52.222-36 Equal Opportunity for Workers with Disabilities.

52.225-7 Waiver of Buy American Statute for Civil Aircraft and Related Articles.

52.227-5 Waiver of Indemnity.

52.228-15 Performance and Payment Bonds-Construction.

52.228-4 Workers’ Compensation and War-Hazard Insurance Overseas.

52.232-12 Advance Payments.

52.237-8 Restriction on Severance Payments to Foreign Nationals.

52.237-9 Waiver of Limitation on Severance Payments to Foreign Nationals.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

252.225-7062 Restriction on Acquisition of Large Medium-Speed Diesel Engines.

252.209-7011 Representation for Restriction on the Use of Certain Institutions of Higher Education.

252.225-7063 Restriction on Acquisition of Components of T-AO 205 and T-ARC Class Vessels.

252.225-7064 Restriction On Acquisition of Certain Satellite Components.

252.270-7001 Pilot Program to Incentivize Contracting with Employee-Owned Businesses—Subcontracting Certification.

252.270-7002 Pilot Program to Incentivize Contracting with Employee-Owned Businesses.

252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.

252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense Contract-Related Felonies.

252.225-7016 Restriction on Acquisition of Ball and Roller Bearings.

252.225-7019 Restriction on Acquisition of Anchor and Mooring Chain.

252.225-7032 Waiver of United Kingdom Levies-Evaluation of Offers.

252.225-7033 Waiver of United Kingdom Levies.

252.242-7005 Contractor Business Systems.

252.247-7023 Transportation of Supplies by Sea.

1852.204-76 Security Requirements for Unclassified Information Technology Resources.

1852.227-70 New Technology-Other than a Small Business Firm or Nonprofit Organization.

1852.227-71 Requests for Waiver of Rights to Inventions.

1852.227-88 Government-furnished computer software and related technical data.

1852.228-76 Cross-Waiver of Liability for International Space Station Activities.

1852.228-78 Cross-Waiver of Liability for Science or Space Exploration Activities Unrelated to the International Space Station.

1852.234-2 Earned Value Management System.

1852.245-78 Physical inventory of capital personal property

5252.204-9503 Expediting Contract Closeout (NAVAIR)

5252.209-9513 ORGANIZATIONAL CONFLICT OF INTEREST INSTRUCTIONS (SERVICES) (NAVAIR)

5252.209-9510 ORGANIZATIONAL CONFLICTS OF INTEREST (SERVICES) (NAVAIR)(MAR 2007)

3052.209-70 Prohibition on contracts with corporate expatriates

5152.225-5902 Fitness for Duty and Medical/Dental Care Limitations

652.228-71 Worker’s Compensation Insurance (Defense Base Act) - Services.

752.231-71 Salary supplements for HG employees.

952.209-72 Organizational conflicts of interest.

952.227-84 Notice of right to request patent waiver.

952.250-70 Nuclear hazards indemnity agreement.

952.227-13 Patent rights—acquisition by the Government.

970.5227-9 Notice of Right To Request Patent Waiver

970.5227-10 Patent rights—management and operating contracts, nonprofit organization or small business firm contractor.

970.5227-12 Patent rights-management and operating contracts, for-profit contractor, patent waiver.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!