GSA 552.236-15 Schedules for Construction Contracts. Alt II (Mar 2019) (Current)

As prescribed in 536.515, insert the clause at 552.236-15, Schedules for Construction Contracts, in solicitations and contracts if construction, dismantling, demolition, or removal of improvements is contemplated. Use the clause-

      (a)  With its Alternate I when the contract amount is expected to be above the simplified acquisition threshold and a design-bid-build project delivery method will be followed; or

      (b)  With its Alternate II when the contract amount is expected to be above the simplified acquisition threshold and a design-build project delivery method will be followed.

      (c)  With its Alternate III when the contract amount is expected to be above the simplified acquisition threshold and a construction-manager-as-constructor project delivery method will be followed.
 

Schedules for Construction Contracts Alternate II (Mar 2019)

The requirements, of the clause entitled “Schedules for Construction Contracts” at FAR 52.236-15, are supplemented as follows:

      (a)  Purpose. The project schedule shall be a rational, reasonable, and realistic plan for completing the work, and conform to the requirements specified in this clause and elsewhere in the contract. The Contractor understands and acknowledges that the preparation and proper management of the project schedule is a material component of the contract.

      (b)  Use of the schedule. The Contracting Officer shall be entitled, but not required, to rely upon the project schedule to evaluate the Contractor's progress, evaluate entitlement to extensions of time, and determine the criticality or float of any activities described in such project schedule.

     (c) Submission. Within 30 calendar days of notice to proceed, or such other time as may be specified in the contract, the Contractor shall submit the project schedule, together with a written narrative describing the major work activities, activities on the critical path, and major constraints underlying the sequence and logic of the project schedule.

      (d)  Milestones. The project schedule shall incorporate milestone events specified in the contract, including, as applicable, notice to proceed, substantial completion, and milestones related to specified work phases and site restrictions. The project schedule shall also include Contractor-defined milestones to identify target dates for critical events, based upon the Contractor's chosen sequence of work.    

(e) Activities.

    (1) The Contractor shall use a critical path method project schedule to plan, coordinate, and perform the work.

    (2) The project schedule shall depict all activities necessary to complete the work, including, as applicable, all submittal and submittal review activities, all procurement activities, and all field activities, including mobilization, construction, start-up, testing, balancing, commissioning, and punchlist.

    (3) Activities shall be sufficiently detailed and limited in duration to enable proper planning and coordination of the work, effective evaluation of the reasonableness and realism of the project schedule, accurate monitoring of progress, and reliable analysis of schedule impacts.

    (4) Activity durations shall be based upon reasonable and realistic allocation of the resources required to complete each activity, given physical and logistical constraints on the performance of the work. All logic shall validly reflect physical or logistical constraints on relationships between activities. Except for the first and last activities in the project schedule, each activity shall have at least one predecessor and one successor relationship to form a logically connected network plan from notice to proceed to the contract completion date.

      (f)  Schedule of values.

           (1)  The Contractor shall prepare and submit for approval a cost breakdown of the Contract price, to be referred to as the “schedule of values”, assigning values to each major activity necessary to complete the work.

           (2)  Values must include all direct and indirect costs, although a separate value for bond costs may be established.

           (3)  The schedule of values must contain sufficient detail to enable the Contracting Officer to evaluate applications for payment.

      (g)  Conflicting terms.

           (1)  If at any time the Contracting Officer finds that the project schedule does not comply with any contract requirement, the Contracting Officer will provide written notice to the Contractor.

           (2)  Within 30 calendar days of written notice, or such other time as may be specified, from the Contracting Officer, the Contractor shall take one of the following actions:

                (i)  Revise the project schedule.

                (ii)  Adjust activity progress.

                (iii)  Provide sufficient information demonstrating compliance.

           (3)  If the Contractor fails to sufficiently address the Contracting Officer's exceptions to the project schedule, the Contracting Officer may-

                (i)  Withhold retainage until the project is substantially complete or until such time as the Contractor has complied with project schedule requirements; or

                (ii)  Terminate the contract for default.    

(h) Revisions to the schedule.

    (1) The Contractor should anticipate that the initial submittal of the project schedule will be subject to review and may require revision. The Contractor shall devote sufficient resources for meetings, revisions, and resubmissions of the project schedule to address any exceptions taken to the initial submittal. The Contractor understands and acknowledges that the purpose of the initial review and resolution of exceptions is to maximize the usefulness of the project schedule for contract performance.

    (2) If the Contractor revises the project schedule after initial approved submission, the Contractor shall provide in writing a narrative describing the substance of the revision, the rationale for the revision, and the impact of the revision on the projected substantial completion date and the available float for all activities. The addition of detail to prospective activities shall not be deemed a revision if the overall duration of the detailed activity does not change.

(i) Updates. Unless a different period for updates is specified elsewhere, the Contractor shall update the project schedule monthly to reflect actual progress in completing the work, and submit the updated project schedule within 5 working days of the end of each month.

(End of clause)
 

NONE

Prime’s Interest;
Services ✖ Supplies ✖ C/R ✖ Time and Materials ✖ Demolition ✔ Construction ✔ Architect-Eng ✖ 
✔ +52.236-15 Basic

52.209-1 Qualification Requirements.

52.246-1 Contractor Inspection Requirements.

52.246-11 Higher-Level Contract Quality Requirement.

52.246-12 Inspection of Construction.

52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements.

52.246-14 Inspection of Transportation.

52.246-15 Certificate of Conformance.

52.246-16 Responsibility for Supplies.

52.246-2 Inspection of Supplies-Fixed-Price.

52.246-3 Inspection of Supplies-Cost-Reimbursement.

52.246-4 Inspection of Services-Fixed-Price.

52.246-5 Inspection of Services-Cost-Reimbursement.

52.246-6 Inspection-Time-and-Material and Labor-Hour.

52.246-7 Inspection of Research and Development-Fixed-Price.

52.246-8 Inspection of Research and Development-Cost-Reimbursement.

52.246-9 Inspection of Research and Development (Short Form).

52.247-4 Inspection of Shipping and Receiving Facilities.

52.248-3 Value Engineering-Construction.

52.246-26 Reporting Nonconforming Items.

52.204-26 Covered Telecommunications Equipment or Services-Representation.

52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services.

52.213-4 Terms and Conditions—Simplified Acquisitions (Other Than Commercial Products and Commercial Services).

52.223-23 Sustainable Products and Services.

52.204-28 Federal Acquisition Supply Chain Security Act Orders-Federal Supply Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts.

252.225-7065 Restriction on Acquisition of Fuel for Overseas Contingency Operations.

252.232-7018 Progress Payments-Multiple Lots.

252.217-7005 Inspection and Manner of Doing Work.

252.228-7005 Mishap Reporting and Investigation Involving Aircraft, Missiles, and Space Launch Vehicles.

252.239-7000 Protection Against Compromising Emanations.

252.215-7015 Program Should-Cost Review.

1852.246-71 Government Contract Quality Assurance.

1852.246-72 Material Inspection and Receiving Report.

1852.246-74 Contractor Counterfeit Electronic Part Detection and Avoidance

5252.246-9512 INSPECTION AND ACCEPTANCE (NAVAIR)(OCT 2005)

5252.246-9514 INSPECTION AND ACCEPTANCE OF TECHNICAL DATA AND INFORMATION (NAVAIR)(FEB 1995)

5252.246-9503 Significance of Systems Engineering Technical Reviews Required under this Contract (NAVAIR)

3052.217-92 Inspection and manner of doing work (USCG).

3052.217-96 Title (USCG).

3052.217-100 Guarantee (USCG).

5152.236-5900 Electrical and Structural Building Standards for Construction Projects

552.238-119 Single-use Plastic (SUP) Free Packaging Availability.

552.238-120 Economic Price Adjustment—Federal Supply Schedule Contracts.

552.270-9 Inspection—Right of Entry.

552.211-70 Substantial Completion.

552.246-70 Source Inspection by Quality Approved Manufacturer.

552.236-11 Use and Possession Prior to Completion.

552.236-6 Superintendence by the Contractor.

552.236-21 Specifications and Drawings for Construction.

552.238-95 Separate Charge for Performance Oriented Packaging (POP).

552.238-96 Separate Charge for Delivery within Consignee's Premises.

552.238-100 Transshipments.

552.238-109 Authentication Supplies and Services.

552.238-110 Commercial Satellite Communication (COMSATCOM) Services.

752.226-70 Trade and Investment Activities and the ‘‘Impact on U.S. Jobs’’ and ‘‘Workers’ Rights.’’

752.231-72 Conference Planning and Required Approval

752.239-71 Information and Communication Technology Accessibility.

752.227-71 Planning, Collection, and Submission of Digital Information to USAID.

752.242-71 Activity Monitoring, Evaluation, and Learning Plan.

752.7003 Documentation for Payment.

752.7006 Notices.

752.7007 Personnel Compensation.

752.7010 Conversion of U.S. Dollars to Local Currency.

752.7015 Use of Pouch Facilities.

752.7025 Approvals.

752.7030 Inspection Trips by Contractor's Officers and Executives.

970.5204-3 Access to and ownership of records.

52.204-30 Federal Acquisition Supply Chain Security Act Orders-Prohibition.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!