NASA 1852.234-2 Earned Value Management System. Alt I (Nov 2006) (Current)

As prescribed in 1834.203-70(b), except for firm-fixed price contracts and the contracts identified in 1834.201(c), the contracting officer shall insert—the clause at 1852.234-2, Earned Value Management System, in solicitations and contracts with a value exceeding $50M that include the provision at 1852.234-1. The contracting officer shall use the clause with its Alternate I when the contract value is less than $50M.

(ALTERNATE I) (NOV 2006)

As prescribed in 1834.203-70(b), substitute the following paragraph (b) for paragraph (b) of the basic clause:

(b) If, at the time of award, the Contractor’s EVMS has not been determined by the Cognizant Federal Agency to be compliant with the EVMS guidelines, or the Contractor does not have an existing cost/schedule control system that is compliant with the guidelines in the ANSI/EIA-748 Standard (current version at the time of ward), the Contractor shall apply the system to the contract and shall take timely action to implement its plan to be compliant with the guidelines. The Government will not formally validate/accept the Contractor’s EVMS with respect to this contract. The use of the Contractor’s EVMS for this contract does not imply Government acceptance of the Contractor’s EVMS for application to future contracts. The Government will monitor compliance through routine surveillance.

NONE, but (f), the Contractor shall be responsible for ensuring that its subcontractors, identified below, comply with the EVMS requirements of this clause as follows: (1) For subcontracts with an estimated dollar value of $50M or more, the following subcontractors shall comply with the requirements of this clause. (Contracting Officer to insert names of subcontractors or subcontracted effort). (2) For subcontracts with an estimated dollar value of less than $50M, the following subcontractors shall comply with the requirements of this clause except for the requirement in paragraph (b), if applicable, to obtain compliance/validation. (Contracting Officer to insert names of subcontractors or subcontracted effort.)

Mandatory (Exception);
FFP ✖ 

52.203-16 Preventing Personal Conflicts of Interest.

52.209-3 First Article Approval-Contractor Testing.

52.209-4 First Article Approval-Government Testing.

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services.

52.215-17 Waiver of Facilities Capital Cost of Money.

52.219-18 Notification of Competition Limited to Eligible 8(a) Participants.

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns.

52.219-6 Notice of Total Small Business Set-Aside.

52.219-7 Notice of Partial Small Business Set-Aside.

52.222-36 Equal Opportunity for Workers with Disabilities.

52.225-7 Waiver of Buy American Statute for Civil Aircraft and Related Articles.

52.227-5 Waiver of Indemnity.

52.228-15 Performance and Payment Bonds-Construction.

52.228-4 Workers’ Compensation and War-Hazard Insurance Overseas.

52.232-12 Advance Payments.

52.234-4 Earned Value Management System.

52.237-8 Restriction on Severance Payments to Foreign Nationals.

52.237-9 Waiver of Limitation on Severance Payments to Foreign Nationals.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

52.209-13 Violation of Arms Control Treaties or Agreements-Certification.

252.225-7062 Restriction on Acquisition of Large Medium-Speed Diesel Engines.

252.209-7011 Representation for Restriction on the Use of Certain Institutions of Higher Education.

252.225-7063 Restriction on Acquisition of Components of T-AO 205 and T-ARC Class Vessels.

252.225-7064 Restriction On Acquisition of Certain Satellite Components.

252.215-7010 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data.

252.203-7001 Prohibition on Persons Convicted of Fraud or Other Defense Contract-Related Felonies.

252.225-7016 Restriction on Acquisition of Ball and Roller Bearings.

252.225-7019 Restriction on Acquisition of Anchor and Mooring Chain.

252.225-7032 Waiver of United Kingdom Levies-Evaluation of Offers.

252.225-7033 Waiver of United Kingdom Levies.

252.242-7005 Contractor Business Systems.

252.247-7023 Transportation of Supplies by Sea.

1852.204-76 Security Requirements for Unclassified Information Technology Resources.

1852.227-70 New Technology-Other than a Small Business Firm or Nonprofit Organization.

1852.227-71 Requests for Waiver of Rights to Inventions.

1852.227-88 Government-furnished computer software and related technical data.

1852.228-76 Cross-Waiver of Liability for International Space Station Activities.

1852.228-78 Cross-Waiver of Liability for Science or Space Exploration Activities Unrelated to the International Space Station.

1852.245-78 Physical inventory of capital personal property

5252.204-9503 Expediting Contract Closeout (NAVAIR)

5252.209-9513 ORGANIZATIONAL CONFLICT OF INTEREST INSTRUCTIONS (SERVICES) (NAVAIR)

5252.209-9510 ORGANIZATIONAL CONFLICTS OF INTEREST (SERVICES) (NAVAIR)(MAR 2007)

3052.209-70 Prohibition on contracts with corporate expatriates

5152.225-5902 Fitness for Duty and Medical/Dental Care Limitations

652.228-71 Worker’s Compensation Insurance (Defense Base Act) - Services.

752.231-71 Salary supplements for HG employees.

952.209-72 Organizational conflicts of interest.

952.227-84 Notice of right to request patent waiver.

952.250-70 Nuclear hazards indemnity agreement.

Working with a set of FAR clauses from an RFP or contract?

Try pasting them into our tool to instantly generate a risk profile, including the basic flow down recommendation.

Info

Works best with Chrome and Edge browsers!